Before digging, who should you contact and how much notice is required?

  1. Call the local police department; 48 hours

  2. Contact Dig Safe; 72 hours

  3. Notify your neighbor; 24 hours

  4. Check with the city office; 12 hours

The correct answer is: Contact Dig Safe; 72 hours

Contacting Dig Safe before digging is essential because it helps prevent accidents and damages to underground utility lines. The requirement to give at least 72 hours' notice ensures that utility companies have adequate time to locate and mark the underground utilities in the area where the work will be done. This notification process is critical for safety, as it reduces the risk of striking utility lines, which can lead to accidents, injuries, and costly repairs. The other options, while suggesting other avenues for notification, do not meet the legal or safety standards established for excavation work. The local police department or city office may not have the necessary information about utility lines, and notifying a neighbor does not ensure the safety and compliance needed before digging. Thus, contacting Dig Safe is the correct procedure to follow.